gabo Systemtechnik speed•pipe® bundle ground Laying instructions SRV-G und SRV-G tc 48 The SRV-G tc must be wound off the coil as described in the illustration (see picture). It is particularly important to respect the linear laying under tension (spool slowed down in controlled manner). Besides these laying instructions also possible existing instructions of the customer concerning the ploughing in of SRV-G tc, ducts or cables must be considered. Note INSTALLATION RECOMMENDATION*: surface trench bottom SRV-G tc laying direction SRV-G tc spool ploughing in * Special conditions on the construction site or laying process may differ from the recommended principle. 17.2 Ploughing.