gabo Systemtechnik Laying instructions. 14 speed•pipe® bundle SRV 50 / 8 x 10 Laying instructions. 6.3 Pulling in the speed•pipe® bundle SRV 50 / 8 x 10. • The speed•pipe® bundle SRV 50 / 8 x 10 is pulled in by means of a traction rope or a tube snake. • Assistance at the coil end may be required as well as at the launching / pulling manhole. • It is to be avoided that the speed•pipe® bundle is placed at the direct access area of the manholes. Therefore, consider the deflection (see page 17) at drawn through or connected SRV. • In case of short distances between the manholes the SRV can be drawn through using protective sheets and pulling spouts. • In case the KKR is to be occupied with two speed•pipe® bundles, these can be pulled in one after the other or at the same time. • The use of lubricant (e. g. Polywater J-19 V Gel; Polywater SP – 128 V Flu) is reducing the pulling in friction.